Pages

Tuesday, November 10, 2020

COMPLETED: Lee/Horan Hall - Brief Network Outage - 11/30 - 10am

UPDATE: As of 11am on 11/30/2020, this maintenance has been completed.

____________________________

UPDATE: This maintenance has been postponed until after the Thanksgiving holiday break. The maintenance will now be conducted on Monday, November 30, 2020 at 10am.

____________________________

Physical Plant will be conducting a generator test in Lee Hall and Horan Hall on Wednesday, November 25th. The generator test will commence in Horan Hall first at 9am, followed by Lee Hall at 10am.

There will be two brief outages, one while switching to generator power, the other while switching back to main power. Both wired and wireless will be affected during this generator test.

Only Lee and Horan Halls will be affected during this generator test. This will not affect the rest of campus.

If you have any questions, please contact ITS at its@manhattan.edu. We apologize for this inconvenience.